Date |
Milestone |
July 12, 2017 |
Issue RFQ |
July 20, 2017 |
Pre-SOQ Submittal Meeting |
August 7, 2017 |
Deadline for Questions on the RFQ |
August 25, 2017 |
SOQ Submittal Date |
October 13, 2017 |
RFQ Short-listed Results |
October 23, 2017 |
Issue RFP to Short-listed teams |
October 30, 2017 |
Issue Draft Design-Build Contract to Short-listed teams |
November 2, 2017 |
Pre-Proposal Meeting |
December 1, 2017 |
Addendum No. 5 Issued to the short-listed teams. |
December 5, 2017 |
Proposal Submittal Date |
December 18, 2017 |
Interviews |
December 22, 2017 |
Selection notification letters sent to RFP Proposers |
January-February 2018 |
Contract negotiations (ongoing) |
February 8, 2018 |
Final Selection Notification sent to James W. Fowler Co. |
February 20, 2018 |
City Council awarded contract to James W. Fowler Co. |
June 2, 2021 |
Contract Amendment for Early Works Package |
August 2021 |
Contract Amendment for GMP |
October 2021 |
Start Construction |
|