| Date |
Milestone |
| July 12, 2017 |
Issue RFQ |
| July 20, 2017 |
Pre-SOQ Submittal Meeting |
| August 7, 2017 |
Deadline for Questions on the RFQ |
| August 25, 2017 |
SOQ Submittal Date |
| October 13, 2017 |
RFQ Short-listed Results |
| October 23, 2017 |
Issue RFP to Short-listed teams |
| October 30, 2017 |
Issue Draft Design-Build Contract to Short-listed teams |
| November 2, 2017 |
Pre-Proposal Meeting |
| December 1, 2017 |
Addendum No. 5 Issued to the short-listed teams. |
| December 5, 2017 |
Proposal Submittal Date |
| December 18, 2017 |
Interviews |
| December 22, 2017 |
Selection notification letters sent to RFP Proposers |
| January-February 2018 |
Contract negotiations (ongoing) |
| February 8, 2018 |
Final Selection Notification sent to James W. Fowler Co. |
| February 20, 2018 |
City Council awarded contract to James W. Fowler Co. |
| June 2, 2021 |
Contract Amendment for Early Works Package |
| August 2021 |
Contract Amendment for GMP |
| October 2021 |
Start Construction |
|