| What's New | |
| October 2021 | Start Construction |
| August 2021 | Contract Amendment for GMP |
| June 2, 2021 | Contract Amendment for Early Works Package |
| April 16, 2018 | Contract Appendix 1 Tables A1-1 and A1-2 added to the website under Document Transfer tab |
| February 20, 2018 | City Council awarded contract to James W. Fowler Co. (teamed with Kennedy Jenks Consultants) |
| February 8, 2018 | Final Selection Notification to James W. Fowler Co. |
| January-February 2018 | Contract negotiations (ongoing) |
| December 22, 2017 |
Selection Notification
Selection notification letter sent to IMCO |
| December 18, 2017 | Interviews |
| December 5, 2017 | Proposal Submittal Deadline |
| December 1, 2017 | Addendum No. 5 Issued to the short-listed teams. |
| November 28, 2017 | Addendum No. 4 Issued to the short-listed teams. Question and Answers No. 2 Issued to the short-listed teams. |
| November 21, 2017 | Addendum No. 3 Issued to the short-listed teams. |
| November 8, 2017 |
Addendum No. 2 Issued to the short-listed teams. Question and Answers No. 1 Issued to the short-listed teams. |
| October 30, 2017 | Addendum No. 1 Issued to the short-listed teams. This Addendum added Volume II – Draft Design-Build Contract and Appendices 1-11. |
| October 23, 2017 | Request For Proposal issued to short-listed teams. |
| October 13, 2017 | RFQ Short-listed results are available at: ES17-0269F RFQ Shortlisting Results.pdf |
| August 29, 2017 | SOQ Submittal Deadline, preliminary results are available at: http://cms.cityoftacoma.org/Purchasing/FormalBidResults/08-29-17ES17-0269F_PreliminarySubmittals.pdf |
| August 15, 2017 |
Addendum No. 3 Issued Questions & Answers No. 2 Issued (note that all RFQ related materials, including addendums, are available at: http://www.cityoftacoma.org/cms/One.aspx?portalId=169&pageId=2259) |
| August 3, 2017 |
Addendum No. 2 Issued Questions & Answers No. 1 Issued (note that all RFQ related materials, including addendums, are available at: http://www.cityoftacoma.org/cms/One.aspx?portalId=169&pageId=2259) |
| July 13, 2017 | Addendum No. 1 Issued - (note that all RFQ related materials, including addendums, are available at: http://www.cityoftacoma.org/cms/One.aspx?portalId=169&pageId=2259) |
| July 12, 2017 |
REQUEST FOR QUALIFICATIONS Issued. RFQ available for download at: http://www.cityoftacoma.org/cms/One.aspx?portalId=169&pageId=2259 An optional Pre-SOQ Submittal Meeting is scheduled for July 20, 2017, at 2:00 p.m. The meeting will be held at:
Tacoma Municipal Building |
| June 13, 2017 | Web site created. |